Adjiringanor: How a US$ 2million compensation claim dispute is delaying construction of overpass at ‘Asamoah Gyan’

The construction of the overpass at Adjiringanor in Accra has been suspended, leading to significant traffic congestion for motorists, especially near the Shell Filling Station, commonly known as Asamoah Gyan.

Potholes at the underpass are adding to the inconvenience.

The Minister of Roads, Governs Kwame Agbodza, last week in an interview on Accra-based Joy FM, revealed that the project is at a halt due to a dispute over a US$2 million compensation claim by two land owners, whose properties have to be demolished either partially by touching a fence wall or completely.

He indicated that with one of the buildings, an uncompleted one, there was nothing on the land when the road project started, but the developer quickly put up the project and is now demanding the compensation. 


Our newsletter gives you access to a curated selection of the most important stories daily. Don't miss out. Subscribe Now.

Connect With Us : 0242202447 | 0551484843 | 0266361755 | 059 199 7513 |