FPSO Kwame Nkrumah to shut down for repairs
Oil and gas production on the Jubilee Fields will be shut down from the first week in May this year to enable engineers to carry out repairs on the production platform, the Floating, Production, Storage and Offloading (FPSO) vessel, Kwame Nkrumah.
The shutdown is part of a programme by the Jubilee partners to continue a remedial plan to correct the defective mooring system (anchoring system) of the vessel.
This will be the fourth time the production platform will be shut down in three years. Its first shutdown in 2016 exacerbated the power shortage problem the country was facing at the time.
Advertisement
Meanwhile, the government has given an assurance that power generation and supply will not suffer any shortfall during this shutdown because the country’s second independent oil field, the Tweneboa, Enyenra and Ntomme (TEN) Fields, will fill the void to sustain the supply of gas to onshore gas processing plants at Atuabo to feed thermal generation units at Aboadze.
A Deputy Minister of Petroleum, Dr Mohammed Amin Adam, gave an assurance in Takoradi last Monday when he joined stakeholders in the power sector on a tour of the FPSO Kwame Nkrumah ahead of its second planned shutdown.
Second shutdown this year
Briefing the media after the tour, Dr Adam said the gas export system of the TEN fields were already connected to the flow lines that transmitted gas to the Atuabo gas processing facility and was ready to export more than 60 million standard cubic feet (mmscf) of gas daily for processing.
He said although in the past the shutdowns had led to some shortfall, the current plan would be well covered and the country would not feel the effect.
He said the first shutdown for this year was last month and it coincided with the schedules of Ghana Gas and, therefore, came with slight hitches.
“I must say that with the current plan, we are safe. In the previous shutdown, although gas was available from TEN, the main processor, Ghana Gas, unfortunately shut down for its mandatory planned maintenance and, therefore, could not receive and process gas,” he added.
Advertisement
That situation, he said, compelled the national power generator, the Volta River Authority (VRA), to resort to expensive light crude oil for power generation.
Currently, Mr Adam said, the Ghana Gas plant was ready to receive gas from TEN.
“I can assure the nation that there will be a seamless shift from the day of the shutdown to the day of restoration of production,” he stressed.
Scope of work
The Managing Director of the lead operator of the Jubilee Fields, Tullow Ghana, Mr Charles Darku, took the stakeholders through the scope of work to get the mooring system back in shape.
Advertisement
He described the previous shutdowns as successful and gave an idea about the partners’ preparation for this year’s second shutdown in May.
As the lead operator, he said, Tullow would continue to offer efficient production operations, while working on a permanent solution, which, he explained involved converting the FPSO into a spread-moored vessel.
Background
In June 2016, Tullow and its partners established the long-term need to convert the FPSO into a permanently spread-moored facility.
Advertisement
The Jubilee turret remediation work is progressing as planned and the FPSO was spread-moored on its current heading in February 1, 2018.
The partners set the next phase of the project to involve the stabilisation of the turret bearing which would take between four and six weeks of shutdown in the first quarter of 2018.
The capital costs associated with the remediation works are being covered by the Joint Venture Hull and Machinery insurance policy.
Advertisement
The final phase will involve rotating the FPSO to its permanent heading and carrying out the final spread-mooring, to take place by the end of 2018.